At 13:42 on July 2, with the No. 3 pile of the No.
36 fan position smoothly sinking to the design level, it has been completed that
the steel pipe pile sinking project for 28 out of the 29 fan positions of the
Putian Shicheng offshore wind farm project. The remaining 4 steel pipe piles at
No. 16 fan position need to wait for the proper tide level to construct. According
to statistics, 10 fan positions are currently undergoing pile foundation
drilling and platform construction, and 4 fan positions are undergoing fan
hoisting operations. Up to now, 13 fan positions have completed the pouring of
the caps and 3 fan positions have been successfully connected to the grid for
power generation. Project chief designer Yang Baoliu and deputy project
chief designer Zhang Qianglin actively communicate with all parties, organize and
coordinate personnel. The Shicheng offshore wind power design team, with party
members as the main force, play the pioneering role and fighting spirit of
party members, actively follow up the progress of the project, and complete the
detailed design work of the construction drawing stage of the project on
schedule in May 2020 to provide guarantee for the smooth progress of the
construction. As the grid connection date approaches, project
construction has entered a critical stage. The design team will continue to
provide technical support for the smooth operation of the project on schedule
with full enthusiasm and solid work.
|